Traffic & Signalization Crew
|
|
|
The signalization division will be adding the adaptive video system to Randal Wobbe Ln. This will include camera and equipment replacement along with some additional wiring. That will be a total of 9 intersections within the adaptive corridor from Randall Wobbe to Don Tyson Parkway. We hope to have this complete by the beginning of April.
FLASHING BEACONS BAYYARI ELEMENTARY

The Traffic & Signalization crew installed solar powered flashing school zone beacons at Bayyari Elementary in late Summer of 2010.
FIBER NETWORK INSTALLATION

The Traffic & Signalization crew extended our fiber network from our location on Randall Wobbe Lane to City Administration on Springs Street in early Summer of 2010.
|
|
| |
|
|
|
|
|
|
|
|
|
| |
| |
|