CIP Projects

There are several projects underway in Springdale to build and improve our infrastructure. For more information about current projects, please contact the Engineering Department at 479-750-8105.  

Project(s)   Project Description Status
Springdale Municipal Airport Regional Detention    This project includes constructing an approximately 10 acre detention facility for the purposes of flood control in Spring Creek, and installing 70 LF of box culvert for storm drainage. Construction in Progress
56th South Phase II Ex. A The overall 56th Street South project includes extending Gene George Boulevard from the existing roundabout at Don Tyson Parkway south to Johnson Mill Boulevard in the City of Johnson.
Phase 2 will incorporate the same amenities while providing a roundabout connection to New Hope Road (approximately 0.45 miles of boulevard and 0.25 miles of New Hope extension).

Land Acquisition
56th South Phase III Ex. A Phase 3 will have the same amenities with a connection to Johnson Mill Boulevard (approximately 0.4 miles of boulevard).  Designed
Don Tyson Parkway West    This project will extend Don Tyson Parkway as a four lane boulevard from the Gene George roundabout to Highway 112. This project will include a landscaped median, sidewalk, a 10 foot sidepath, and a connection into the 64th Street Phase 2 project. The city is also planning for ArDOT to connect Don Tyson with the Highway 112 roundabout. Total approximate length: 0.8 miles Right of Way Acquisition
phasing map
Exhibit A: 56th South Phase I-III