40th Street - 18BPS4

40th Street will be widened from Falcon Road north to the Spring Creek bridge as a three-lane road with a center turn lane.

Alerts

  1. There are no alerts at this time.

Sign up through Notify Me to receive alerts for this project.

  1. Ryan Carr

    Deputy Director of Engineering Operations
    Phone: 479-750-8105

40th st

Project Updates

  1. Status
  2. Contractors
Phase Details Phase Est. Completion
Please note that all dates are subject to change
Design 100% Complete Spring 2019
Right-of-Way Acquisition Reed and Associates currently working on appraising the properties. Plans have been sent to franchise utilities for relocation designs.  Spring 2020