Dixieland Road - 18BPS14

This is a project to extend Dixieland Road from Apple Blossom to Wagon Wheel as a three-lane road.  The public input session for this project is set for December 12, 2019 in the Council Chambers at City Hall. 

Alerts

  1. There are no alerts at this time.

Sign up through Notify Me to receive alerts for this project.

  1. Ryan Carr

    Deputy Director of Engineering Operations
    Phone: 479-750-8105

Project Updates

  1. Status
  2. Contractors
Phase Details Phase Est. Completion
Please note that all dates are subject to change
Alignment study Garver Complete
Traffic Study/ Surveying Garver  Fall 2019
Design 90% complete Spring 2020
Land Acquisition    Spring 2021