Dixieland Road Extension
Updates:
Status: 85% Complete
Description: This project extends Dixieland Road from Apple Blossom to Wagon Wheel as a three-lane road. This project will include sidewalk, a 12 foot sidepath with pedestrian refuge islands, and a traffic signal at the Wagon Wheel intersection. No connection to Hiland Road is proposed at this time. Total approximate length: 1 mile
Estimated Date of Completion: Spring 2024
Current Contract Amount: $7,540,117.35